The following are the Quantity Of Materials Required for different types of Civil Engineering Works ;-

1) Brickwork in Cement Mortar (1:6)

For 10 cu.m. Of Brickwork in Cement Mortar (1:6) The Consumption Of Materials are
With Modular Bricks :-
Bricks @ 5000 Nos.
Cement @ 0.504 cu.m. or 15 Bags
Sand @ 3.02cu.m. or 87 Bags
With Traditional Bricks :-
Bricks @ 4079 Nos.
Cement @ 0.313 cu.m. or 9 Bags
Sand @ 1.88cu.m. or 54 Bags

2) Brickwork in Cement Mortar (1:4)

With Modular Bricks :-
For 100 Sq.m.100mm thick Brickwork in Cement Mortar (1:4) The Consumption Of Materials are
Bricks @ 5000 Nos.
Cement @ 0.63 cu.m. or 19 Bags.
Sand @  2.52 cu.m. or 73 Bags
With Traditional Bricks :-
For 100 Sq.m.127mm thick Brickwork in Cement Mortar (1:4) The Consumption Of Materials are
Bricks @ 5181 Nos.
Cement @ 0.80 cu.m. or 23 Bags.
Sand @ 3.20 cu.m. or 92 Bags

Add Comment

Bulletin Board Concrete Technology Estimating Costing Contract & Valuation Geoinformatics Geotechnical Engineering Materials & Construction Public Health Engineering Road Engineering Structural Engineering
Surveing Featured Image
Geoinformatics and Surveying Definition and Classification
Bituminous Road
Importance of Temperature Controlling in Bituminous Road Work
Flat Slab and Ribbed or Waffle Slab Secrets
Bricks Concrete
Brick Test
Field Tests Of Building Materials
Cube Testing Mould
Concrete Cube Test To Determine Concrete Strength
Water Absorption Test
Water Absoption Test Of Bricks – Laboratory Method
Quiz Logo
Civil Engineering Interview Skill Test Free