The following are the Quantity Of Materials Required for different types of Civil Engineering Works ;-

1) Brickwork in Cement Mortar (1:6) ===>

For 10 cu.m. Of Brickwork in Cement Mortar (1:6) The Consumption Of Materials are
With Modular Bricks :-
Bricks @ 5000 Nos.
Cement @ 0.504 cu.m. or 15 Bags
Sand @ 3.02cu.m. or 87 Bags
With Traditional Bricks :-
Bricks @ 4079 Nos.
Cement @ 0.313 cu.m. or 9 Bags
Sand @ 1.88cu.m. or 54 Bags

2) Brickwork in Cement Mortar (1:4) ===>

With Modular Bricks :-
For 100 Sq.m.100mm thick Brickwork in Cement Mortar (1:4) The Consumption Of Materials are
Bricks @ 5000 Nos.
Cemnent @ 0.63 cu.m. or 19 Bags.
Sand @  2.52 cu.m. or 73 Bags
With Traditional Bricks :-
For 100 Sq.m.127mm thick Brickwork in Cement Mortar (1:4) The Consumption Of Materials are
Bricks @ 5181 Nos.
Cement @ 0.80 cu.m. or 23 Bags.
Sand @ 3.20 cu.m. or 92 Bags

Follow Techno Genome at :-

Add Comment

Concrete Technology Constructional Materials and Practices Geoinformatics Geotechnical Engineering Job & How To Structural Engineering Transportation Engineering Water Resources & Public Health Engineering
Temperature Controlling in Bituminous Road Construction
Concrete Strength and Importance of Water
Online Civil Engineering Tutorials
Concrete Testing Material Testing Soil Testing
Field Tests Of Building Materials
Concrete Cube Test To Determine Concrete Strength
Drying Oven
Water Absoption Test Of Bricks – Laboratory Method