Materials Required For ASF, Plastering & Neat Cement

Last Updated on

Neat Cement Punning

 

Here is how to become a Concrete Calculator by yourself for different types of concrete operation like concrete floor , plaster wall , ceiling plaster, cement finishing etc. works.

1) Artificial Stone Flooring ===>

The Quantity of materials required for 100 Sq.m. 25mm Thick Artificial Stone Flooring 3mm Topping is

Cement @ 0.859 or 25 Bags
Sand @ 0.97 cu.m or 28 Bags
Stone Chips (6mm and Down) @ 1.94 cu.m or 56 Bags

2) Cement and Sand Plastering===>

For 100 Sq.m Of Plastering the required Quantity Of Materials are :
With Cement Mortar (1:6) :-
12mm thick ——–    Cement = 0.274 cu.m or 8 Bags             Sand = 1.64 cu.m. or 48 Bags
15mm thick ——–    Cement = 0.342 cu.m. or 10 Bags          Sand = 2.05 cu.m. or 59 Bags
20mm thick ——–    Cement = 0.456 cu.m. or 13 Bags          Sand = 2.74 cu.m. or 79 Bags
With Cement Mortar (1:4) :-
10mm thick ——–    Cement = 0.319 cu.m. or 9 Bags            Sand = 1.29 cu.m. or 37 Bags
6mm thick  ———   Cement = 0.192 cu.m. or 6 Bags             Sand = 0.77 cu.m. 22 Bags

3) Neat Cement Punning===>

Quantity Of Materials Required for 100 Sq.m. Of Neat Cement Punning is as follows:-
1.5mm Thick ——-    Cement = 0.186 cu.m. or 5.5 Bags
3mm Thick    ——-    Cement = 0.375 cu.m. or 11 Bags
6mm Thick    ——-    Cement = 0.750 cu.m. or 22 Bags

Follow Techno Genome at :-

Add Comment

Concrete Technology Constructional Materials and Practices Geoinformatics Geotechnical Engineering Job & How To Structural Engineering Transportation Engineering Water Resources & Public Health Engineering
Temperature Controlling in Bituminous Road Construction
Concrete Strength and Importance of Water
Online Civil Engineering Tutorials
Concrete Testing Material Testing Soil Testing
Field Tests Of Building Materials
Concrete Cube Test To Determine Concrete Strength
Drying Oven
Water Absoption Test Of Bricks – Laboratory Method